Cubic Yard Calculator

Cubic Yard Calculator uses length, width or area, depth, and quantity to find cu yd: cubic yards = cubic feet ÷ 27, with cost, material weight, and 5–10% extra order estimates for bulk material tasks.

ft
ft
in
Qty
$
Total Cubic Yards Required
1.23 cu yd
The bulk volume measure used for material ordering.
Estimated Weights
Concrete: 2.47 tons
Gravel / Stone 1.73 tons
Topsoil / Dirt 1.36 tons
Approximate weights using default density factors; actual weight varies by material, moisture, and compaction.
Material Cost
$148.15
Unit Price $120.00 / cu yd
Cost Each $148.15
Projected material costs based on total calculated volume and specified market rate.
Area & Base Volume
100.00 sq ft
Depth Used 4.00 in
Cubic Feet 33.33 cu ft
Geometric breakdowns mapping the horizontal surface coverage and precise inner volumetric capacities.
Ordering Extra
0.06 – 0.12 cu yd
5% Extra Order 1.30 cu yd
10% Extra Order 1.36 cu yd
Recommended additional material to account for grade variations, spills, and settling.
Material Estimation Note
One cubic yard equals 27 cubic feet (e.g., an area of 3 ft by 3 ft, 3 ft deep). It is industry standard to order 5–10% extra material for unlevel subgrades, compaction, and edge spillage.

Why Cubic Yards Trip People Up

Concrete suppliers quote in cubic yards. Your tape measure gives you feet and inches. That gap — and specifically the inch-to-yard conversion buried inside it — is where most over-orders and under-orders happen. A 4-inch slab sounds thin, but converting that to a fraction of a yard before multiplying means three unit jumps in one calculation. One slip and you’re either short on pour day or paying a return-trip fee on a half-loaded truck.

This calculator handles that conversion chain for you and adds material weight estimates, a cost projection, and a waste-factor buffer — the outputs you actually need before calling a ready-mix plant or placing a material order.

How the Volume Is Calculated

The core formula is straightforward: Area × Depth = Volume. What changes depending on your inputs is how area gets derived and which unit conversions run before the final cubic-yard figure appears.

In US Customary mode, depth is entered in inches and divided by 12 internally to convert it to feet. That keeps your length and width entries in feet without asking you to think in decimals. The resulting cubic feet total is then divided by 27 — because one cubic yard is exactly 3 ft × 3 ft × 3 ft — to give you cubic yards.

In Metric mode, depth is entered in centimeters and divided by 100 to get meters. Area times depth gives cubic meters, which are then multiplied by 1.3079 to reach cubic yards. The calculator always outputs cubic yards as the primary figure because that’s the standard ordering unit for bulk materials in most markets regardless of how you measured the site.

For rectangular areas, area is length × width. For circular areas, you enter the diameter and the calculator derives radius internally before applying π r². If you already know the square footage — say you’ve measured an irregular shape in your head or with another tool — the Area per Section mode lets you skip the geometry and enter square footage directly.

The Quantity field multiplies everything. Enter 3 if you’re pouring three identical footings. It accepts only whole numbers, which reflects real-world ordering: you’re not pouring 2.5 sections.

What the Weight Estimates Represent

Three weight figures appear automatically — one for concrete, one for gravel or crushed stone, and one for topsoil. These use fixed density multipliers: 2.0 short tons per cubic yard for concrete, 1.4 tons/CY for gravel, and 1.1 tons/CY for topsoil. They’re approximations. Actual weight shifts with moisture content, aggregate type, and compaction. Wet topsoil and dry sand can differ by 30% or more. Use these numbers for load planning and truck-weight estimates — not for structural engineering decisions.

A Real Pour: Residential Driveway Approach

The apron at the bottom of a driveway — where it meets the street — is one of the most common small concrete jobs. A typical approach runs about 12 feet wide and 8 feet deep from the curb to the garage pad edge, poured at 6 inches thick to handle vehicle load.

  • Shape: Rectangle, Length 12 ft, Width 8 ft
  • Depth: 6 in
  • Quantity: 1

Area = 96 sq ft. Depth in feet = 0.5. Volume = 48 cu ft ÷ 27 = 1.78 cubic yards. At $130/CY that’s $231. With a 10% buffer to cover edge spill and any low spots in the subgrade, the order should be 1.96 CY — most contractors round to 2.0 CY and call it done. The weight estimate of roughly 3.56 tons matters here if the ready-mix truck needs to drive across a lawn to reach the pour site.

The Waste Buffer — and When to Ignore It

The calculator shows a 5% and 10% extra-order figure alongside the base volume. The 5–10% range is a widely cited rule of thumb for concrete and fill work, accounting for subgrade irregularities, form overfill, and spill. For a slab on a well-graded base with tight forming, 5% is usually sufficient. For topsoil or gravel spread over uneven ground, 10% is conservative but reasonable.

There’s one case where you should ignore these numbers entirely: if the supplier’s minimum order is larger than your 10% buffer total anyway. Ready-mix plants often have a 1-CY minimum charge. If your project needs 0.8 CY, order 1 CY — not 0.88 with a 10% buffer applied. The buffer logic only matters once your base volume exceeds the delivery minimum.

The Entry That Gets Entered Wrong Most Often

Depth in US mode is in inches, not feet. That’s intentional — slab thickness is almost universally called out in inches on drawings and in conversation (“pour it at four inches”). But if you’re calculating something like a retaining wall footing that’s 18 inches deep, or a gravel base that’s specified as 1.5 feet, it’s easy to type the feet value out of habit. Entering 1.5 when you mean 18 inches produces a volume roughly 12 times smaller than the actual job requires. Check the unit label next to the depth field before calculating — it will say “in” in US mode and “cm” in metric mode.

Frequently Asked Questions

My area isn’t a clean rectangle or circle — what shape should I choose?

Use Area per Section. Measure or estimate your irregular area in square feet (or square meters), enter that figure, set your depth, and the volume calculation runs from there. This mode is also useful when you have a site plan that already shows square footage — no need to reverse-engineer the dimensions.

Why does switching between US and Metric reset my inputs?

The default values change when the unit system changes because 10 feet and 10 meters represent very different areas — keeping the same numbers would produce a misleading result. The reset is intentional. Re-enter your measurements in the new unit system before calculating.

The price field is blank — does that affect the volume result?

No. Price is optional and only drives the cost output in Card 2. The cubic yard total, weight estimates, and ordering buffer all calculate the same way with or without a price entered. Leave it blank if you’re still getting quotes.

Do the weight estimates account for compaction?

They don’t. The densities used (2.0 tons/CY for concrete, 1.4 for gravel, 1.1 for topsoil) are uncompacted bulk approximations. Compacted gravel can run 10–15% heavier per cubic yard than loose fill. If you’re specifying by weight for a structural fill layer, get the compacted density from your material data sheet and calculate manually.

Can I calculate multiple different sections in one go?

Only if the sections are identical — the Quantity field multiplies the same dimensions by a whole number count. If you have sections of different sizes (say, two footings at 2×2 ft and three at 3×3 ft), run separate calculations and add the cubic yard totals before placing your order.