Cement Calculator turns a wet volume, slab size or area into bags of cement, with sand, gravel, water and cost, for concrete mixes from 1:5:10 to 1:1:2 or a sand and cement mortar.
Enter the wet volume, the finished volume in place. Dry factor, waste and bag size are set below.
Mix Details and Bags
Parts are by volume. Set gravel to 0 for mortar. The dry factor turns wet volume into loose materials.
Prices and Water
Prices are samples. The water ratio is the IS 456 maximum for the mix picked, or 0.5 where none is listed.
Cement by Mix Ratio
| Mix | 94 lb Bags | Sand | Gravel |
|---|---|---|---|
| 1:1:2 | 11 | 0.42 cu yd | 0.85 cu yd |
| 1:1.5:3 | 8 | 0.46 cu yd | 0.92 cu yd |
| 1:2:3 | 8 | 0.56 cu yd | 0.85 cu yd |
| 1:2:4 | 7 | 0.48 cu yd | 0.97 cu yd |
| 1:3:6 | 5 | 0.51 cu yd | 1.02 cu yd |
| 1:4:8 | 4 | 0.52 cu yd | 1.04 cu yd |
| 1:5:10 | 3 | 0.53 cu yd | 1.06 cu yd |
Bags for Common Slabs
| Slab, 4 in Thick | 94 lb Bags | Wet Volume |
|---|---|---|
| Your job | 8 | 1.00 cu yd |
| 10 × 10 ft | 10 | 1.23 cu yd |
| 12 × 12 ft | 15 | 1.78 cu yd |
| 20 × 20 ft | 40 | 4.94 cu yd |
| 1,000 sq ft | 99 | 12.35 cu yd |
What the Cement Calculator Works Out
The Cement Calculator opens on 1 cu yd of 1:1.5:3 concrete. That mix needs 8 bags of cement in 94 lb US bags, rounded up from 7.95, with 10% waste included. Switch the volume to cubic meters and the bag changes to 50 kg.
The result also lists 748 lb of cement, 0.462 cu yd of sand, 0.924 cu yd of gravel and 53.7 gal of water. Sand and gravel are shown by weight too, at 1,246 lb and 2,492 lb. At the sample prices the mix costs $186.99.
You can enter the job five ways. Type a wet volume, a slab as length by width by thickness, an area with a thickness, a round column or hole, or a brick wall for its mortar. The tool runs in a phone browser, so there is no app to install.
Cement Calculator Formula
Cement quantity starts from the wet volume, the finished concrete in place. Loose cement, sand and gravel take up more room than the mixed concrete, because water closes the voids between them. The dry volume factor covers that.
The 1.54 factor is a common site figure for concrete, and the tool lets you change it. Mortar and plaster use 1.33. Waste is added next, then the cement takes its share of the total by the mix ratio.
The letters c, s and g are the cement, sand and gravel parts. Cement volume is turned into weight at a bulk density of 1,440 kg per cubic meter, which is 90 lb per cubic foot and the unit weight listed for cement in IS 875 Part 1. The weight divided by the bag size gives the bags.
Here is the default job by hand. One cubic yard times 1.54 is 1.54 cu yd dry. Adding 10% waste gives 1.694 cu yd. A 1:1.5:3 mix has 5.5 parts, so cement is 0.308 cu yd. That weighs 748 lb, or 339 kg, which is 7.95 bags of 94 lb or 6.78 bags of 50 kg.
Bags of Cement by Mix Ratio
A richer mix uses more cement for the same volume. The table gives bags for each preset before waste, so you can compare mixes directly. It also answers how many 50 kg bags go into 1 cubic meter of concrete.
| Mix, cement : sand : gravel | 94 lb bags per cu yd | 50 kg bags per cu m | Cement per cu m | Grade in IS 456 |
|---|---|---|---|---|
| 1:1:2 | 9.94 | 11.09 | 554 kg | Not a nominal mix |
| 1:1.5:3 | 7.23 | 8.06 | 403 kg | M20 |
| 1:2:3 | 6.63 | 7.39 | 370 kg | Not a nominal mix |
| 1:2:4 | 5.68 | 6.34 | 317 kg | M15 |
| 1:3:6 | 3.98 | 4.44 | 222 kg | M10 |
| 1:4:8 | 3.06 | 3.41 | 171 kg | M7.5 |
| 1:5:10 | 2.49 | 2.77 | 139 kg | M5 |
So 1 cubic meter of 1:1.5:3 concrete takes 8.06 bags of 50 kg, and 9 bags once 10% waste is added. Used as a 1:2:4 concrete mix calculator, the Cement Calculator gives 6.34 bags per cubic meter, or 5.68 US bags per cubic yard.
The tool shows the same figure for your own job as bags per cubic yard before waste. For the default mix that is 7.23, and one 94 lb bag makes 3.73 cu ft of finished concrete.
The grade column follows the usual pairing of volume ratios with the nominal mixes in IS 456. That code allows nominal mix concrete only for M20 or lower. Stronger concrete needs a designed mix, which is why the tool marks 1:1:2 as 25 MPa typical.
Water comes from the same table in IS 456. It caps water at 30 liters per 50 kg bag for M20 and 32 liters for M15, which are ratios of 0.60 and 0.64. The Cement Calculator loads that cap for the mix you pick. The Water To Cement Ratio Calculator works on the ratio alone.
If you only need the split for a known volume, the Concrete Mix Calculator breaks a concrete volume into cement, sand, gravel and water in one step.
Cement Calculator Square Feet Chart
For a slab, choose Area and Thickness, or enter the length and width. The chart is for a 4 in slab in 1:1.5:3 concrete with 10% waste. The last column shows the leaner 1:2:4 mix.
| Slab area, 4 in thick | Wet volume | 94 lb bags | 50 kg bags | 50 kg bags, 1:2:4 |
|---|---|---|---|---|
| 50 sq ft | 0.62 cu yd | 5 | 5 | 4 |
| 100 sq ft, 10 x 10 | 1.23 cu yd | 10 | 9 | 7 |
| 144 sq ft, 12 x 12 | 1.78 cu yd | 15 | 13 | 10 |
| 300 sq ft | 3.70 cu yd | 30 | 26 | 20 |
| 400 sq ft, 20 x 20 | 4.94 cu yd | 40 | 34 | 27 |
| 900 sq ft | 11.11 cu yd | 89 | 76 | 60 |
| 1,000 sq ft | 12.35 cu yd | 99 | 84 | 66 |
| 1,200 sq ft | 14.81 cu yd | 118 | 101 | 79 |
A 10 x 10 slab is 100 square feet and needs 10 US bags or 9 bags of 50 kg, with 0.57 cu yd of sand and 1.14 cu yd of gravel. A 12 x 12 slab needs 15 US bags. A 20 x 20 slab needs 40, and a 1,000 sq ft slab needs 99.
To calculate cement per sq ft, divide the bags by the area. At 4 in thick, each square foot takes 0.084 of a 50 kg bag or 0.098 of a 94 lb bag. Turned around, one 50 kg bag covers about 12 sq ft of 4 in slab.
A 900 sq ft house needs more than its floor slab. The 89 US bags, or 76 bags of 50 kg, in the chart cover one 4 in slab of that size. Footings, columns, walls and plaster each need their own run, and the bags are added together.
The chart counts site-mixed concrete. If you are buying premixed bags or ready mix for a 10 x 10 slab, the Concrete Calculator gives the 1.23 cu yd as yards and bag counts.
Sand and Cement Calculator for Mortar and Walls
Set I Want to Mix to Mortar or Plaster. The gravel drops out and the dry factor changes to 1.33. The Cement Calculator then works as a sand and cement calculator for plaster, screed and bedding.
| Mortar mix, cement : sand | 94 lb bags per cu yd | 50 kg bags per cu m | Sand per cu m of mortar |
|---|---|---|---|
| 1:3 | 8.59 | 9.58 | 1.00 cu m |
| 1:4 | 6.87 | 7.66 | 1.06 cu m |
| 1:5 | 5.72 | 6.38 | 1.11 cu m |
| 1:6 | 4.91 | 5.47 | 1.14 cu m |
For plaster on a wall, enter the wall area and the coat thickness. A 100 sq ft wall with a 1/2 in coat of 1:4 plaster needs 1.17 US bags or one 50 kg bag, and 4.9 cu ft of sand. So one 94 lb bag of cement covers about 86 sq ft of 1/2 in plaster.
As a cement calculator for a wall, the tool has a Brick Wall Mortar option. Enter the wall face area, pick the brick and set the joint. It works out the joint volume for a wall one brick thick and sets the mix to mortar.
US modular brick with a 3/8 in joint holds 5.5 cu ft of mortar per 100 sq ft of wall. In 1:4 mortar that is 1.55 US bags of cement and 6.5 cu ft of sand, so buy 2 bags. A 1,000 sq ft wall needs 16 bags and 2.4 cu yd of sand.
Those are bags of plain cement mixed with loose sand. Premixed mortar bags already hold the sand, and the Brick Calculator counts them with the bricks. For block walls and other joint sizes, use the Mortar Calculator.
Sand is often bought first, and cement is matched to it. For 100 cft of sand, a 1:4 mortar needs 25 cft of cement, which is 20.4 bags of 50 kg. A 1:6 mortar needs 13.6 bags. In 1:2:4 concrete the same sand goes with 40.8 bags.
Cement Bag Sizes, Cft and Weight
A bag of cement is 94 lb, or 43 kg, in the United States, according to the American Concrete Institute. Many other countries, India among them, sell 50 kg bags, with 40 kg and 25 kg bags for small jobs. The Cement Calculator offers all of these, a 47 lb half bag, and a custom bag weight in kg or lb.
A 50 kg bag holds 1.226 cft of loose cement at 1,440 kg per cubic meter. That is 0.0347 cubic meters, or 34.7 liters. A 94 lb bag holds 1.05 cu ft at the same density.
Sand and gravel weights in the results assume dry material at 1,600 kg per cubic meter, about 100 lb per cubic foot. IS 875 Part 1 lists dry sand at 1,540 to 1,600 and loose gravel at 1,600. Damp loads weigh more.
One cubic meter is not always 1,000 kg. That is true for water only. A cubic meter of loose cement weighs 1,440 kg at the density the tool uses, which is why 1 cubic meter of cement is 28.8 bags of 50 kg.
How to calculate 1 cft
One cft is one cubic foot. Multiply length, width and depth in feet to get it. There are 27 cft in a cubic yard and 35.31 cft in a cubic meter, and 1 cft of sand is 28.3 liters by volume.
A square foot has no fixed cft, because cft needs a depth. One sq ft at 4 in thick is 0.333 cft, and at 12 in thick it is 1 cft. In Indian trade use, one unit of sand, also called a brass, is 100 cft.
Cost of Cement, Slabs and RCC
Cement cost is the whole bags times the price of one bag. The Cement Calculator opens with a sample price of $15 per bag, so 20 bags of cement come to $300. Prices differ by brand, bag weight and region, so enter the price you are quoted for one bag.
The price of a 30 kg, 50 kg or 94 lb bag is set by the seller. For a 30 kg bag, choose Custom Bag Weight and enter its price. The default job then takes 12 bags. To compare bag sizes, divide each price by its weight.
A 10 x 10 cement slab costs $232.70 in materials at the sample prices. That is 10 US bags at $15, plus sand at $45 and gravel at $50 per cubic yard. Delivery, forms and labor are extra.
RCC for 1,000 square feet comes to $2,312.04 for cement, sand and gravel at the same prices, for a 4 in slab with 99 US bags. RCC also needs steel, which the tool does not price. The Rebar Calculator gives the bar count, length and weight.
Materials to Lay a 12x12 Concrete Slab
A 12x12 concrete slab at 4 in thick is 48 cu ft, or 1.78 cu yd. In 1:1.5:3 concrete it needs 13 bags of 50 kg or 15 bags of 94 lb. It also takes 0.82 cu yd of sand, 1.64 cu yd of gravel and about 96 gal of water.
Set the forms and the base before you mix, and give the slab a fall so water runs off. The Concrete Slope Calculator finds the drop across 12 ft. A thickened edge or a footing under the slab is extra volume, which the Concrete Footing Calculator covers.