Excavation slope calculator for OSHA soil types A, B, and C: setback per side, top width, wall angle, trench or pit volume, distressed walls, trench boxes and the ladders required.
Pick the soil type a competent person classified, then enter the excavation size.
Excavation Cross-Section Diagram
OSHA Excavation Slope Chart
| Soil | Max Slope | Angle | Setback | Top Width | Volume |
|---|---|---|---|---|---|
| Stable Rock | 0:1 | 90° | 0 in | 3 ft | 44.4 cu yd |
| Type A (24 h) | 1/2:1 | 63° | 4 ft | 11 ft | 103.7 cu yd |
| Type A | 3/4:1 | 53° | 6 ft | 15 ft | 133.3 cu yd |
| Type B | 1:1 | 45° | 8 ft | 19 ft | 163.0 cu yd |
| Type C | 1 1/2:1 | 34° | 12 ft | 27 ft | 222.2 cu yd |
Step-by-Step Excavation Slope Math
- Max slope for Type C = 1 1/2:1 (33.69°) from OSHA Table B-1
- Top width = 3 ft + 2 × 12 ft = 27 ft
- Slope face = √(8² + 12²) = 14.422 ft
- Area = 3 ft × 8 ft + 2 × wall wedges = 120.0 sq ft; volume = area × 50 ft = 222.2 cu yd
- Ladders = 50 ft ÷ 50 ft (25 ft travel each way) → 1; length = 8 ft ÷ 0.968 (foot set out 1/4 of its length) + 3 ft = 11.262 ft
- Loose spoil = 222.2 cu yd × (1 + 25%) = 277.8 cu yd
- If distressed: slope 2:1 (26.57°) gives setback 16 ft and 281.5 cu yd
- Setback per side = 8 ft × 1.5 = 12 ft = 12 ft
Excavation Slope Calculator Setback on an 8 ft Trench
An 8 ft deep trench in Type C soil needs each wall cut back 12 ft, so a 3 ft bottom opens to 27 ft at the top. Over 50 ft that sloped trench holds 222.2 cu yd (169.9 m³) of soil in place.
Type C is the default classification under OSHA's sloping option, and it is the slope to use until a competent person tests the soil. An excavation slope calculator estimate should start from that soil type and the depth.
S is the setback per side, D the depth, k the horizontal part of the slope ratio (1.5 for 1.5:1), Wb the bottom width, Wt the top width and F the length of the sloped wall face.
| Result | Math | Value |
|---|---|---|
| Setback per side | 8 ft x 1.5 | 12 ft |
| Top width | 3 + 2 x 12 | 27 ft |
| Wall face length | √(8² + 12²) | 14 ft 5 1/8 in |
| Wall angle | arctan(1 / 1.5) | 33.69° |
| Cross-section area | 3 x 8 + 12 x 8 | 120 sq ft |
| Volume per foot | 120 / 27 | 4.44 cu yd |
| Volume over 50 ft | 120 x 50 / 27 | 222.2 cu yd |
| Loose spoil at 25% swell | 222.2 x 1.25 | 277.8 cu yd |
| Spoil toe from bottom edge | 12 + 2 | 14 ft |
With vertical walls, the same 50 ft trench in an excavation slope calculator estimate would be only 44.4 cu yd. Sloping makes the Type C trench five times the vertical-wall volume, and that extra digging is the cost to weigh against a trench box.
The rules behind these excavation slope calculator numbers come from OSHA 29 CFR 1926 Subpart P, Appendix B. They apply to excavations 20 ft deep or less; anything deeper needs a design from a registered professional engineer.
OSHA Soil Types and Setback by Depth
OSHA allows vertical walls in stable rock, 3/4:1 (53°) in Type A, 1:1 (45°) in Type B and 1 1/2:1 (34°) in Type C. That is the OSHA excavation slope chart every trench plan starts from.
For an excavation slope calculator estimate, Type A soil may use 1/2:1 (63°) when the cut is 12 ft deep or less and stays open 24 hours or less. Past 12 ft the short-term slope reverts to 3/4:1.
| Depth | Type A, short term | Type A | Type B | Type C | Type C top width (3 ft bottom) |
|---|---|---|---|---|---|
| 5 ft | 2 ft 6 in | 3 ft 9 in | 5 ft | 7 ft 6 in | 18 ft |
| 6 ft | 3 ft | 4 ft 6 in | 6 ft | 9 ft | 21 ft |
| 8 ft | 4 ft | 6 ft | 8 ft | 12 ft | 27 ft |
| 10 ft | 5 ft | 7 ft 6 in | 10 ft | 15 ft | 33 ft |
| 12 ft | 6 ft | 9 ft | 12 ft | 18 ft | 39 ft |
| 15 ft | 11 ft 3 in | 11 ft 3 in | 15 ft | 22 ft 6 in | 48 ft |
| 20 ft | 15 ft | 15 ft | 20 ft | 30 ft | 63 ft |
Excavation slope calculator setbacks are per side. A 20 ft Type C trench takes 63 ft of ground width, which is why deep cuts on tight sites rarely slope at all.
Metric excavation slope calculator work uses the same ratios. At 2 m deep, setback is 1.00 m short term, 1.50 m in Type A, 2.00 m in Type B and 3.00 m in Type C, so a 0.9 m bottom opens to 6.90 m in Type C.
At 3 m the Type C setback is 4.50 m and the top 9.90 m. At 4 m the short-term Type A slope no longer applies, and both Type A rows reach 3.00 m per side.
The soil type behind any excavation slope calculator answer comes from tests. Under Appendix A, Type A is cohesive soil with at least 1.5 tsf (144 kPa) unconfined compressive strength, and Type C is 0.5 tsf (48 kPa) or less.
Fissures, vibration from traffic, earlier digging or layers dipping into the cut at 4:1 or steeper drop a strong soil out of Type A. Freely seeping water or submerged soil makes it Type C, whatever its strength.
Trench and Pit Volume With Sloped Walls
An 8 ft trench 50 ft long holds 133.3 cu yd in Type A, 163.0 in Type B and 222.2 in Type C, against 44.4 with vertical walls. Volume grows with depth squared, so doubling depth more than triples the soil.
For a trench, the excavation slope calculator cross-section is a trapezoid and the volume is that area times the length. The ends are usually left vertical against shoring or the next run of pipe.
| Depth | Stable rock | Type A | Type B | Type C | Type C per foot |
|---|---|---|---|---|---|
| 5 ft | 27.8 | 62.5 | 74.1 | 97.2 | 1.94 |
| 6 ft | 33.3 | 83.3 | 100.0 | 133.3 | 2.67 |
| 8 ft | 44.4 | 133.3 | 163.0 | 222.2 | 4.44 |
| 10 ft | 55.6 | 194.4 | 240.7 | 333.3 | 6.67 |
| 12 ft | 66.7 | 266.7 | 333.3 | 466.7 | 9.33 |
| 16 ft | 88.9 | 444.4 | 563.0 | 800.0 | 16.00 |
| 20 ft | 111.1 | 666.7 | 851.9 | 1,222.2 | 24.44 |
These excavation slope calculator values are bank cubic yards for a 50 ft trench with a 3 ft bottom. Dug soil swells, so the spoil pile and the truck loads are larger than the hole.
The 222.2 bank yards of the 8 ft Type C trench become 250.0 loose yards in dry sand at 12.5% swell, 277.8 in dry packed earth at 25% and 319.6 in topsoil at 43.8%, using the Caterpillar earthwork tables.
Truck loads for that loose volume, with the truck weight limit checked as well as bed volume, come from the Cut And Fill Calculator.
A pit slopes on all four sides, so its corners add soil that a trench-only excavation slope calculator formula misses. Its volume follows the prismoidal rule, which weights the middle slice four times.
Ab is the bottom area, At the top area and Am the area at mid-depth, each found from the bottom size plus twice the setback at that level. D is the depth.
A 10 ft by 10 ft pit 8 ft deep in Type C opens to 34 ft by 34 ft and holds 157.6 cu yd. Treating it as a 10 ft length of trench gives 65.2 cu yd, less than half, because the sloped ends and corners are ignored.
That gap is the usual reason excavation volume calculator with slope estimates come in low. Any pit dug for a basement or tank needs the four-sided figure.
Distressed Walls Add Half a Unit of Slope
Once a wall shows fissures, slumping or ravelling, OSHA requires it cut back at least 1/2:1 flatter than the maximum. On the 8 ft Type C trench that moves the slope to 2:1, the setback from 12 ft to 16 ft and the volume up by 59.3 cu yd.
The added half unit puts 4 ft more setback per side on any 8 ft cut, so the extra soil is the same 59.3 cu yd for every soil type at that depth and length. The angle change is what differs.
| Soil | Normal setback | Distressed setback | Distressed angle | Volume, normal to distressed (cu yd) |
|---|---|---|---|---|
| Stable rock | 0 ft | 4 ft | 63° | 44.4 to 103.7 |
| Type A, short term | 4 ft | 8 ft | 45° | 103.7 to 163.0 |
| Type A | 6 ft | 10 ft | 39° | 133.3 to 192.6 |
| Type B | 8 ft | 12 ft | 34° | 163.0 to 222.2 |
| Type C | 12 ft | 16 ft | 27° | 222.2 to 281.5 |
A distressed Type B wall ends up at the plain Type C slope in any excavation slope calculator check. Planning the excavation slope calculator top width for the next softer class keeps room at the edge if rain or vibration opens cracks mid-job.
Rain is the usual trigger for redoing an excavation slope calculator check. OSHA 1926.651(k)(1) requires a competent person to inspect daily and after every rainstorm, and seeping water reclassifies the soil as Type C.
Layered Soil: Which Layer Sets the Wall
A weak layer under a stronger one controls the whole wall, while a weak layer on top only flattens its own band. In an 8 ft cut with a 3 ft upper layer, Type C over Type B needs 9 ft 6 in of setback, but Type B over Type C needs the full 12 ft.
Appendix A classifies a layered system by its weakest layer, unless the stronger layer is underneath. Each band then takes its own Table B-1 slope, and the excavation slope calculator setbacks stack.
| Upper 3 ft over lower 5 ft | Setback per side | Top width (3 ft bottom) | Overall angle | Volume, 50 ft (cu yd) |
|---|---|---|---|---|
| Type B over Type A | 6 ft 9 in | 16 ft 6 in | 49.8° | 137.5 |
| Type C over Type A | 8 ft 3 in | 19 ft 6 in | 44.1° | 145.8 |
| Type C over Type B | 9 ft 6 in | 22 ft | 40.1° | 171.3 |
| Type A over Type B | 8 ft | 19 ft | 45.0° | 163.0 |
| Type B over Type C | 12 ft | 27 ft | 33.7° | 222.2 |
| Type A over Type C | 12 ft | 27 ft | 33.7° | 222.2 |
Type C over Type A saves 76.4 cu yd against counting the whole wall as Type C in an excavation slope calculator run. The saving only holds while the lower layer stays dry, so groundwater in the lower band sends the cut back to the full Type C slope.
Benching, Vertical Sides and Trench Boxes
A trench box that leaves 6.5 ft of vertical side in an 8 ft Type C trench cuts the dig from 222.2 to 50.7 cu yd over 50 ft. The shield must stand at least 18 in above the vertical side, with only the upper part sloped.
OSHA allows a supported or shielded vertical lower side in Type A, B and C soil to 20 ft, with the wall above at that soil's maximum slope. An 8 ft box therefore protects a vertical side of 6.5 ft.
| Box height in 8 ft trench | Vertical side | Type A volume | Type B volume | Type C volume | Type C top width |
|---|---|---|---|---|---|
| None (full slope) | 0 ft | 133.3 | 163.0 | 222.2 | 27 ft |
| 4 ft | 2.5 ft | 86.5 | 100.5 | 128.5 | 19 ft 6 in |
| 6 ft | 4.5 ft | 61.5 | 67.1 | 78.5 | 13 ft 6 in |
| 8 ft | 6.5 ft | 47.6 | 48.6 | 50.7 | 7 ft 6 in |
Excavation slope calculator volumes here are cubic yards over 50 ft with a 3 ft bottom. In Type C the 8 ft box saves 171.5 cu yd, and in a 10 ft Type C trench the same box cuts the dig from 333.3 to 89.6 cu yd.
Type A soil alone may keep an unsupported vertical lower side up to 3 1/2 ft. Above it the wall slopes at 3/4:1 when the cut is 8 ft or less, and at 1:1 for cuts over 8 ft up to 12 ft.
On the 8 ft trench in Type A, a 3 1/2 ft vertical side drops the setback from 6 ft to 3 ft 4 1/2 in and the volume from 133.3 to 72.6 cu yd. At 10 ft deep the 1:1 rule leaves a 6 ft 6 in setback, only a foot less than plain 3/4:1.
Benches step the wall but must stay inside the maximum slope line, so a benched wall never gets a smaller excavation slope calculator top width than a simple slope. OSHA's Appendix B gives benched layouts for Type A and Type B and none for Type C.
The Type A short-term slope is the cheapest excavation slope calculator option for a quick shallow job. An 8 ft cut at 1/2:1 removes 103.7 cu yd against 133.3 at 3/4:1, if it is backfilled within 24 hours.
Ladders and Spoil Placement Along the Trench
A trench 4 ft deep or more needs a ladder, stair or ramp within 25 ft of lateral travel, so one ladder serves each 50 ft of trench. An 8 ft trench needs a ladder at least 11 ft 3 1/8 in long.
Excavation slope calculator ladder lengths follow two OSHA rules. 1926.1053 requires the rails to extend 3 ft above the landing and the foot to sit about one quarter of the working length out from the top support.
| Trench depth | Minimum ladder length | Foot out from wall | Trench length | Ladders needed |
|---|---|---|---|---|
| 4 ft | 7 ft 1 5/8 in | 1 ft 3/8 in | 25 ft | 1 |
| 6 ft | 9 ft 2 3/8 in | 1 ft 6 5/8 in | 50 ft | 1 |
| 8 ft | 11 ft 3 1/8 in | 2 ft 3/4 in | 75 ft | 2 |
| 10 ft | 13 ft 3 7/8 in | 2 ft 7 in | 100 ft | 2 |
| 12 ft | 15 ft 4 3/4 in | 3 ft 1 1/8 in | 150 ft | 3 |
| 16 ft | 19 ft 6 1/4 in | 4 ft 1 5/8 in | 200 ft | 4 |
| 20 ft | 23 ft 7 7/8 in | 5 ft 2 in | 300 ft | 6 |
These lengths assume the ladder leans on a vertical face, such as a trench box wall or a vertical lower side, at the one-in-four angle. A ladder laid along a 34° slope is far flatter than that rule allows.
Spoil stays at least 2 ft from the edge under 1926.651(j)(2). On a sloped trench that edge is the top of the slope, so the spoil toe sits the excavation slope calculator setback plus 2 ft from the bottom edge, 14 ft on the 8 ft Type C cut.
The 27 ft top plus a 2 ft clear strip on each side takes 31 ft of ground before any spoil pile. Dig rate for that volume comes from the Excavator Productivity Calculator, and backfill needs from the Fill Dirt Calculator.
Field Answers on Excavation Slopes
Slope ratios on site and in any excavation slope calculator are written horizontal to vertical, so 1 1/2:1 means 1.5 ft out for every 1 ft down. Percent grade and degrees describe the same wall in other units.
How do you calculate excavation slope?
Multiply the depth by the horizontal part of the OSHA ratio for the soil type to get the setback per side, the core of every excavation slope calculator. A 6 ft trench in Type B soil at 1:1 sets back 6 ft each side, so a 3 ft bottom opens to 15 ft.
The slope distance along the wall is the square root of depth squared plus setback squared. For that 6 ft Type B wall it is 8.49 ft, and for an 8 ft Type C wall it is 14 ft 5 1/8 in.
What is an excavation slope?
It is the angle a trench or pit wall is cut back from vertical so the soil cannot cave in. OSHA counts sloping as a protective system alongside benching, shoring and shields for any excavation 5 ft deep or more.
The steepest allowed slope in any excavation slope calculator depends on soil strength, from vertical in stable rock to 34° in Type C. Flatter is always permitted; steeper needs shoring, a shield or an engineer's design.
What is the standard slope for excavations?
The standard is 1 1/2:1, or 34°, because OSHA 1926.652(b)(1) allows it in any soil without classification. Steeper slopes of 1:1 or 3/4:1 need a competent person to classify the soil as Type B or A.
A foundation excavation follows the same excavation slope calculator rule. A 30 ft by 40 ft basement pit 6 ft deep in Type B soil opens to 42 ft by 52 ft at the top and holds 370.7 cu yd.
How do I calculate a safe trench slope?
Start with Type C at 1 1/2:1 unless the soil has been tested, then multiply by the depth for the excavation slope calculator setback. A 5 ft Type C trench needs 7 ft 6 in per side, an 18 ft wide top on a 3 ft bottom.
Trenches under 5 ft need no protective system unless a competent person sees signs of a possible cave-in, and cuts made entirely in stable rock are exempt at any depth. Beyond 20 ft the slope must come from a registered engineer.
What is the formula for excavation?
A sloped trench is (bottom width x depth + setback x depth) x length, which equals the trapezoid area times length. An 8 ft Type C trench with a 3 ft bottom is (3 x 8 + 12 x 8) x 50 = 6,000 cu ft, or 222.2 cu yd.
For a sloped pit, excavation slope calculator volume uses the prismoidal rule because all four sides lean out. Divide cubic feet by 27 for cubic yards, or by 35.31 for cubic metres.
What is the 5 4 3 2 1 rule excavation?
It is a field memory aid built on OSHA numbers, not a rule title in the standard. Protection starts at 5 ft, a ladder is required at 4 ft, the ladder extends 3 ft above the top and spoil stays 2 ft back.
Crews use the final 1 for different things, usually one competent person inspecting daily or one means of exit within each 25 ft of travel. The first four numbers come from 1926.652(a)(1), 1926.651(c)(2), 1926.1053(b)(1) and 1926.651(j)(2).
What angle is a 70% slope?
A 70% slope is 34.99°, about 35°, with a horizontal to vertical ratio of 1.43:1. It sits just steeper than OSHA's Type C maximum of 1 1/2:1 (34°), so a 70% wall needs at least Type B soil.
A 2:1 slope is 50% grade and 26.57°, which is gentler than any OSHA maximum and is the distressed slope for Type C walls.
What is a 2% slope?
A 2% slope falls 2 units for every 100 units of distance, which is 20 mm per metre or 0.24 in per foot. Over 5 m it falls 0.10 m (100 mm), and its angle is only 1.15°.
In excavation slope calculator work, 2% describes the fall of a trench bottom or graded surface for drainage, not the wall. A wall at 2% grade would be almost flat ground.
What is 1% slope in mm?
A 1% slope falls 10 mm per metre, so 30 m of pipe trench drops 300 mm. In feet it is 0.12 in per foot, just under 1/8 in, and the angle is 0.57°.
To set it, multiply the run by 0.01. Laser levels and grade rods read that fall directly, since the angle is too small for a hand level.