Trench Volume Calculator

Updated

Trench volume calculator for straight, sloped or trapezoid trenches, giving bank and loose cubic yards or m3, OSHA wall slope by soil type, pipe bedding, backfill, trucks and cost.

Trench Setup

Straight, vertical walls. Measure the width and depth at the bottom of the cut.

runs
H : 1V
Depth Change Along the RunSame depth
Pipe, Bedding and Backfill6 in pipe
Soil Swell, Weight and Trucks25.5% swell
%
Excavation Cost$8.5 per ft
Trench Volume
29.63 cu yd Trench VolumeVolume
In-place (bank) soil dug out, also 800 cu ft or 22.65 m³
37.19 cu yd Loose SpoilLoose
Truck Loads (14 cu yd)3 loads
Soil Weight47.41 tons
Dug soil fluffs up by the swell factor, so it fills more truck space than the hole it came from.
16.05 cu yd Backfill to ReplaceBackfill
Bedding Stone18.32 tons
Spoil Left to Haul17.04 cu yd
Stone around the pipe takes the place of soil, so that much spoil, swelled, is left over to haul.
200.0 sq ft Top Surface AreaSurface Area
Wall Area, Each Side400.0 sq ft
Cross-Section8.00 sq ft
Ground opened at the top, for restoring sod or paving. Wall area sizes shoring and trench boxes.
$2,015 Excavation CostCost
Cost per Foot$20.15
Stone and Haul-Off$1,165
Digging, bedding stone and hauling off the extra spoil, all at the local prices you entered.
Trench Cross-Section Diagram4 ft deep
Top 2 ftBottom 2 ft4 ftPipe 6 in in stone, 100 ft long
Trench Volume by LengthSame cross-section
LengthVolumeLooseTrucksCost
10 ft2.96 cu yd3.72 cu yd1$201.51
25 ft7.41 cu yd9.30 cu yd1$503.77
50 ft14.81 cu yd18.59 cu yd2$1,008
100 ft29.63 cu yd37.19 cu yd3$2,015
200 ft59.26 cu yd74.37 cu yd6$4,030
500 ft148.1 cu yd185.9 cu yd14$10,075
1,000 ft296.3 cu yd371.9 cu yd27$20,151
Step-by-Step Trench Volume Math8 steps
Cross-section2 ft × 4 ft = 8 sq ft
Trench volume8 sq ft × 100 ft = 800 cu ft ÷ 27 = 29.6296 cu yd
Loose spoil29.6296 cu yd × 1.255 = 37.1852 cu yd, ÷ 14 cu yd per truck = 3 loads
Soil weight29.6296 cu yd × 3,200 lb/cu yd ÷ 2,000 = 47.4074 tons
Pipe zone1.8333 ft high × 2 ft average width × 100 ft = 366.6667 cu ft, minus pipe 19.635 cu ft = 347.0317 cu ft of stone (18.3156 tons)
Backfill800 - 366.6667 = 433.3333 cu ft; spoil left 366.6667 × 1.255 = 460.1667 cu ft loose
Cost$850.00 digging + $824.20 stone + $340.86 haul-off = $2,015.06
Result800 cu ft = 29.63 cu yd
Ladder or Ramp Required
Trenches 4 ft (1.22 m) deep or more need a ladder, stairway or ramp within 25 ft (7.6 m) of every worker. Keep spoil piles at least 2 ft (0.6 m) back from the edge.

Trench Volume Calculator Formula for Vertical and Sloped Walls

A trench 100 ft long, 2 ft wide and 4 ft deep with vertical walls holds 800 cubic feet, or 29.63 cubic yards of soil in place. In a trench volume calculator metric check, 30 m × 0.6 m × 1.2 m is 21.6 m³.

V is the volume, L the trench length, w the bottom width and d the depth, all in the same unit. The side slope k is the horizontal setback per 1 unit of depth, so k is 0 for vertical walls and 1 for a 1:1 slope.

For a trapezoid with known top and bottom widths, the cross-section is the average width times the depth. A ditch 6 m long, 0.6 m wide at the top, 0.4 m at the bottom and 1.2 m deep holds 6 × 0.5 × 1.2 = 3.6 m³.

Divide cubic feet by 27 to get a trench volume calculator cubic yards figure, and multiply cubic meters by 1,000 for liters. A V-ditch uses the same trench volume calculator formula with the bottom width set to zero.

100 ft trench, 2 ft bottom4 ft deepTop width at 4 ft6 ft deepTop width at 6 ft
Vertical walls29.63 cu yd2 ft44.44 cu yd2 ft
3/4:1 slope74.07 cu yd8 ft144.44 cu yd11 ft
1:1 slope88.89 cu yd10 ft177.78 cu yd14 ft
1-1/2:1 slope118.52 cu yd14 ft244.44 cu yd20 ft

Sloped walls grow with the square of depth, so they dominate any deep trench volume calculator result. At 6 ft deep a 1:1 trench moves four times the soil of a vertical one, and a 1-1/2:1 trench moves 5.5 times as much.

Soil Type and OSHA Wall Slopes

A trench 5 ft deep or more needs a protective system, either a trench box, shoring or walls sloped back for the soil. The slope in a trench volume calculator estimate depends on soil type, from vertical in stable rock to 1-1/2:1 in Type C soil.

OSHA 29 CFR 1926 Subpart P, Appendix B sets the maximum slopes for excavations under 20 ft deep. Deeper sloping or benching must be designed by a registered professional engineer.

Soil typeMaximum slope (H:V)AngleVolume, 100 ft × 2 ft × 6 ftVersus vertical
Stable rockVertical90°44.44 cu yd1.0×
Type A, short-term1/2:163°111.11 cu yd2.5×
Type A3/4:153°144.44 cu yd3.25×
Type B1:145°177.78 cu yd4.0×
Type C1-1/2:134°244.44 cu yd5.5×

The 1/2:1 short-term slope applies only to Type A soil 12 ft deep or less. Below 12 ft, Type A drops to 3/4:1 even for a short dig.

Sloping versus a trench box is a cost decision in any trench volume calculator for excavation. The 6 ft Type C trench opens 2,000 sq ft of ground at a 20 ft top width.

A boxed trench of the same depth opens only 200 sq ft, so sod, paving and spoil room all scale with the slope you choose.

The Excavation Slope Calculator works out the top width and setback for each soil type when the slope, not the volume, is the question.

Bank, Loose and Truck Loads

Soil swells once it is dug, so 29.63 cubic yards of common earth in the ground becomes about 37.19 cubic yards in the truck. At 14 cubic yards per load the trench volume calculator count is 3 trucks, and the soil weighs about 47.41 US tons.

The swell comes from the bank and loose weights in Caterpillar's earthwork volume tables. Dry packed earth weighs 3,200 lb per cubic yard in the bank and 2,550 lb loose, so it swells 25.5%.

SoilBank weightLoose weightSwellLoose cu yd from 29.63 bankWeight
Earth, dry packed3,200 lb/yd³2,550 lb/yd³25.5%37.1847.41 tons
Loam2,600 lb/yd³2,100 lb/yd³23.8%36.6838.52 tons
Clay, natural bed3,400 lb/yd³2,800 lb/yd³21.4%35.9850.37 tons
Clay and gravel, dry2,800 lb/yd³2,400 lb/yd³16.7%34.5741.48 tons
Sand and gravel, dry3,250 lb/yd³2,900 lb/yd³12.1%33.2148.15 tons
Sand, dry loose2,700 lb/yd³2,400 lb/yd³12.5%33.3340.00 tons
Topsoil2,300 lb/yd³1,600 lb/yd³43.8%42.5934.07 tons

Topsoil is the trap in any trench volume calculator soil table. It is the lightest soil but swells the most, so the same trench of topsoil needs 4 trucks instead of 3, even though it weighs 13 tons less than common earth.

Truck count always rounds up in a trench volume calculator for construction. Check weight as well as volume on long runs, since 14 cubic yards of loose clay at 2,800 lb per yard is 19.6 tons.

Compare that loaded weight with the truck's rated payload, not just its bed size, before booking loads.

Bedding, Backfill and Spoil Left Over

A 6 in pipe in the 100 ft × 2 ft × 4 ft trench, with 4 in of bedding below and 12 in of stone above, takes about 12.85 cubic yards of stone, or 18.32 tons at 2,850 lb per yard. That leaves 16.05 cubic yards of native soil to backfill.

In trench volume calculator for pipe work, the stone takes the place of dug soil, so the spoil it displaces has to leave the site. Here 13.58 bank cubic yards of pipe zone becomes 17.04 loose cubic yards to haul away, about one truck and a quarter.

Pipe outside diameterMinimum bottom widthBedding stoneStone weightSoil backfillSpoil to haul
4 in20 in12.02 cu yd17.13 tons17.28 cu yd15.49 cu yd
6 in22 in12.85 cu yd18.32 tons16.05 cu yd17.04 cu yd
8 in24 in13.52 cu yd19.27 tons14.81 cu yd18.59 cu yd
12 in28 in14.38 cu yd20.48 tons12.35 cu yd21.69 cu yd

The minimum width is the larger of the pipe OD plus 16 in or 1.25 times the OD plus 12 in, so bedding can be packed under both sides.

It matches the ASTM D2321 table in Prinsco's HDPE trench installation detail, which also calls for 4 in of bedding under 4 to 36 in pipe.

The 24 in trench clears the 22 in minimum for a 6 in pipe, but a 12 in pipe needs 28 in. The Pipe Bedding Calculator works the stone on its own when the trench is already dug.

A trench backfill calculator figure is bank volume, not loose, just like the trench volume calculator total it comes from.

Compacted fill packs tighter than loose spoil, so keep some of the loose pile back rather than hauling everything above the bank figure.

Depth That Changes Along the Run

A sloped trench from 4 ft to 8 ft deep holds more than one dug at an even 6 ft, because the sloped part grows with depth squared.

With a 2 ft bottom and 1:1 walls over 100 ft it holds 182.72 cubic yards, while a trench volume calculator shortcut at the average depth comes to 177.78, a 2.7% undercount.

A is the average cross-section along the run, w the bottom width and d1 and d2 the depths at the two ends. The second term is exact for walls sloped at k when the depth changes evenly along the trench.

The trench volume calculator error from averaging grows with slope and depth change. A Type C trench from 3 ft to 9 ft deep holds 261.11 cubic yards against 244.44 at the average.

That shortcut misses 16.67 bank cubic yards, more than a full 14 yard truck once the soil swells to about 20.9 loose yards.

Vertical walls have no such error. A 4 to 8 ft vertical trench holds exactly the 44.44 cubic yards of a 6 ft one, since only the sloped part of the cross-section grows faster than depth.

Drainage runs are the usual case. The Drainage Fall Calculator gives the drop along a pipe run, which sets the start and end depths for the volume.

Digging, Stone and Haul-Off Cost

At $8.50 per foot to dig, $45 per ton of bedding stone and $20 per loose cubic yard to haul off, the 100 ft pipe trench costs about $2,015, or $20.15 per foot.

In that trench volume calculator cost, digging is $850, stone $824.20 and haul-off $340.86, so stone nearly matches the digging bill.

Trench lengthBank volumeLoose volumeTruck loadsCost
25 ft7.41 cu yd9.30 cu yd1$503.77
50 ft14.81 cu yd18.59 cu yd2$1,007.53
100 ft29.63 cu yd37.19 cu yd3$2,015.06
200 ft59.26 cu yd74.37 cu yd6$4,030.13
500 ft148.15 cu yd185.93 cu yd14$10,075.32
1,000 ft296.30 cu yd371.85 cu yd27$20,150.65

These prices are example inputs, so swap in your own quote for any trench excavation cost estimator total. Bedding stone is the largest line after digging, which is why a narrower trench that still meets the pipe width rule saves real money.

Digging quoted per cubic yard changes the picture for wide trenches. At $12 per cubic yard the same 100 ft trench costs $355.56 to dig instead of $850, while a quote per foot stays the same whatever the width.

The haul-off line covers only the spoil the stone displaced. If none of the native soil goes back in, haul the full 37.19 loose cubic yards, and the Excavator Productivity Calculator estimates how long the dig itself will take.

Measuring, Safety Numbers and Soil Weight

Each answer below works fresh numbers through the same trench volume calculator math as the sections above.

How to calculate volume of trench?

Multiply length by width by depth for a straight-walled trench, then divide cubic feet by 27 for cubic yards. A 50 ft trench 18 in wide and 3 ft deep is 50 × 1.5 × 3 = 225 cubic feet, or 8.33 cubic yards.

For sloped walls, add the slope times the depth squared to the width times depth before multiplying by length. Use the depth at both ends and the trench volume calculation formula above if the trench gets deeper along its run.

What is a trench volume calculator?

It is an excavation estimate of bank cubic yards, loose yards, truck loads and tons, worked from a trench's length, width, depth and wall slope. A trench excavation calculator adds the pipe zone, stone and cost on top.

For the 100 ft × 2 ft × 4 ft trench, the trench volume calculator numbers are 29.63 bank yards, 37.19 loose yards, 3 trucks and 47.41 tons of common earth.

How do you calculate a slop sided trench?

Add the slope's extra width to the vertical-wall cross-section. With a bottom width w, depth d and slope k, the cross-section is w × d plus k × d², and the top width is w plus 2 × k × d.

A 3 ft wide trench 5 ft deep at 1:1 has a cross-section of 15 + 25 = 40 sq ft and a 13 ft top width. Over 60 ft that is 2,400 cubic feet, or 88.89 cubic yards.

How do you measure a trench?

For a trench volume calculator, measure the bottom width and depth at the bottom of the cut, and the length along the centerline.

Take depth at both ends and the middle on long runs before any trench volume calculator estimate, since depth usually changes with grade.

For sloped walls, measure the top width too, or work it out from the soil type. A trench that is 2 ft at the bottom and 10 ft at the top over 4 ft of depth has 1:1 walls.

How much to trench 100 feet?

A 100 ft trench 2 ft wide and 4 ft deep moves 29.63 cubic yards and costs about $2,015 with a 6 in pipe, stone bedding and haul-off at the example prices. Digging alone at $8.50 per foot is $850.

A shallow 1 ft wide, 2 ft deep irrigation trench over 100 ft is only 7.41 cubic yards, and at the same $8.50 per foot costs $850 to dig with no stone or haul-off.

What is the 5 4 3 2 1 rule for trenching?

It is a site memory aid built on OSHA trench numbers, not an OSHA rule in itself. The 5 is the 5 ft depth that needs a protective system, the 4 is the 4 ft depth that needs a ladder or ramp, and the 2 is the 2 ft spoil setback.

The 3 is usually the 3 ft a ladder's side rails must extend above the landing, from OSHA's ladder standard 1926.1053. The meaning of the final 1 varies between training handouts, so rely on the four OSHA figures it stands beside.

What is the 2 4 5 6 in excavation trenching?

It lists four OSHA depths and distances. Keep spoil at least 2 ft from the edge, provide a way out at 4 ft deep within 25 ft of travel, protect the walls at 5 ft deep, and guard walkways 6 ft or more above the trench.

The 4 foot rule is the egress part of that list, from OSHA 1926.651(c)(2). Air must also be tested before entering excavations over 4 ft deep where a hazardous atmosphere may exist.

How to calculate sq ft of a trench?

Multiply length by top width to get the ground area opened, the trench square footage calculator figure for sod or paving. The 100 ft × 2 ft vertical trench opens 200 sq ft, while the same trench at 6 ft deep with 1:1 walls opens 1,400 sq ft.

Wall area matters for shoring. Each wall of the 100 ft × 4 ft vertical trench is 400 sq ft, and each sloped wall of the 6 ft, 1:1 trench is about 849 sq ft.

How much does a cubic yard of excavated soil weigh?

Dry packed earth weighs about 3,200 lb per cubic yard in the ground and 2,550 lb once loose, per Caterpillar's tables. Clay in its natural bed is heavier at 3,400 lb, and topsoil lighter at 2,300 lb.

In metric, dry packed earth is about 1,900 kg/m³ in the bank and 1,510 kg/m³ loose. Wet soil weighs more, since moisture content changes the weight.

What is swell factor and what value should I use?

Swell is the extra volume soil takes up once dug, the bank weight divided by the loose weight minus one. In a trench volume calculator, use about 25% for common earth, 21% for clay, 12% for sand and gravel and 44% for topsoil.

On a 500 ft trench of 148.15 bank yards, 25.5% swell means 185.93 loose yards and 14 trucks. The same trench in topsoil would need about 213 loose yards, so two more loads.

How wide should the bottom of a pipe trench be?

Make the bottom at least the pipe OD plus 16 in, or 1.25 times the OD plus 12 in, whichever is larger. A 6 in pipe needs 22 in, and a 12 in pipe needs 28 in.

Wider pipe drives the second rule in a trench volume calculator for pipe. A pipe with a 24 in OD needs 42 in of bottom width, which is 1.25 × 24 + 12, more than the 40 in from the OD plus 16 in rule.