Dump truck load calculator for tons, yards and trips for a job, set by bed size or federal bridge formula payload, with swell, wet weight, trailers and hauling cost by hour or ton.
Volume as it sits in the ground before digging. It swells once dug, so it fills more of the bed.
Material Weight and Swell
Legal Weight Limit
Hauling Cost and Time
Bed Volume vs Weight Limit
Dump Truck Capacity Chart
| Truck | Bed | Full Bed | Payload | Per Load | Loads |
|---|---|---|---|---|---|
| Tandem axle | 12.00 cu yd | 15.30 tons | 13.25 tons | 13.25 tons | 13 |
| Tri-axle | 16.00 cu yd | 20.40 tons | 15.50 tons | 15.50 tons | 11 |
| Belly dump | 22.00 cu yd | 28.05 tons | 25.00 tons | 25.00 tons | 7 |
| Semi end dump | 29.00 cu yd | 36.98 tons | 24.00 tons | 24.00 tons | 7 |
| 7 × 14 ft dump trailer | 5.28 cu yd | 6.74 tons | 5.43 tons | 5.43 tons | 30 |
Step-by-Step Truck Load Math
Dump Truck Load Calculator Tons and Yards by Truck Type
A truck load is the smaller of two numbers: the weight of a full bed and the legal payload. Divide the job's total tons by that per-load figure and round up to get the number of trips.
Start from weight, because both limits are set in pounds. Dug soil is measured in place, so bank yards become tons through the bank density, then loose yards through the bed density, the order every dump truck load calculator estimate follows.
T is US tons, Vb is bank cubic yards, Db is the bank density in lb/yd³, Vl is loose cubic yards and Dl is the loose density in lb/yd³, all from the same material row.
B is the bed in loose cubic yards, W is the legal gross weight in pounds, E is the empty truck weight and P is tons per load. The ceiling n is the load count, since a part load is still a trip.
Take 100 bank yd³ of dry packed earth at 3,200 lb/yd³ bank and 2,550 lb/yd³ loose, the pair in Caterpillar's earthwork volume tables. That is 160 tons, which swells to 125.49 loose yd³ once dug.
A 12 yd³ tandem holds 15.3 tons when full, but its legal payload at a 20 ft outer bridge is 51,000 minus 24,500 lb, or 13.25 tons. Each load stops at 13.25 tons, which is 10.39 loose yd³ with the bed 86.6% full.
The job takes 160 ÷ 13.25 = 12.08, rounded up to 13 loads, and the last one carries 1.0 ton. A volume-only dump truck load calculator shortcut, 125.49 yd³ over a 12 yd³ bed, gives 11 loads, with every load 2.05 tons over.
| Truck | Bed (yd³) | Full Bed (tons) | Legal Payload (tons) | Per Load (tons) | Loads for 160 Tons |
|---|---|---|---|---|---|
| Tandem, 3 axles, 20 ft | 12 | 15.30 | 13.25 | 13.25 | 13 |
| Tri-axle, 4 axles, 24 ft | 16 | 20.40 | 15.50 | 15.50 | 11 |
| Belly dump, 5 axles, 51 ft | 22 | 28.05 | 25.00 | 25.00 | 7 |
| Semi end dump, 5 axles, 51 ft | 29 | 36.98 | 24.00 | 24.00 | 7 |
| 7 × 14 ft dump trailer, 18 in sides | 5.28 | 6.74 | 5.43 | 5.43 | 30 |
The semi has the larger body yet carries a ton less than the belly dump, because its 32,000 lb tare beats the belly dump's 30,000 lb. Both reach the 80,000 lb cap, so the empty weight sets the payload.
Every truck in the table weighs out on dry earth, so a dump truck load calculator result based on bed volume alone undercounts trips.
Bank yards for the cut itself come from the Cut and Fill Calculator or the Trench Volume Calculator, and those yards feed straight into the weight step above.
Bridge Formula Limits on Gross Weight
A dump truck's maximum gross weight on the Interstate is the smallest of three numbers: the bridge formula for its axles and outer bridge, the sum of its axle limits, and 80,000 lb. The empty weight comes off to leave the payload.
W is the maximum gross weight in pounds on a group of axles, L is the distance in feet from the first to the last axle of that group, and N is the number of axles. The formula is set in 23 CFR 658.17(e).
Results are rounded to the nearest 500 lb, the gross any dump truck load calculator payload starts from.
A 3-axle tandem at 20 ft gives exactly 51,000 lb, a 4-axle tri-axle at 24 ft gives 58,000 lb, and a 5-axle rig at 51 ft gives 79,875 lb, which rounds to 80,000.
| Outer Bridge (ft) | 3 Axles (lb) | 4 Axles (lb) | 5 Axles (lb) |
|---|---|---|---|
| 14 | 46,500 | 51,500 | 56,500 |
| 16 | 48,000 | 52,500 | 58,000 |
| 18 | 49,500 | 54,000 | 59,000 |
| 20 | 51,000 | 55,500 | 60,500 |
| 24 | 54,000 | 58,000 | 63,000 |
| 30 | 54,000 (axles) | 62,000 | 66,500 |
| 35 | 54,000 (axles) | 65,500 | 70,000 |
| 40 | 54,000 (axles) | 68,500 | 73,000 |
| 45 | 54,000 (axles) | 72,000 | 76,000 |
| 51 | 54,000 (axles) | 74,000 (axles) | 80,000 |
Each extra foot of bridge adds 750 lb on 3 axles, 667 lb on 4 and 625 lb on 5. Stretching a tandem from 20 to 24 ft adds 3,000 lb, or 1.5 tons per trip, but past 24 ft it gains nothing more.
The same rule caps any one axle at 20,000 lb and a tandem pair at 34,000 lb. A steer axle plus one tandem pair adds up to 54,000 lb, so a 3-axle truck stops there, and a 4-axle truck stops at 74,000 lb from a 48 ft bridge on.
A 2-axle truck with a wheelbase of 10 ft or more is held to 40,000 lb by its two single axles, since the bridge formula already allows 40,000 at 10 ft. On 5 axles the 88,000 lb axle total sits above the 80,000 lb cap.
Federal limits apply on the Interstate and reasonable access to it. Paragraphs (b) to (d) of 658.17 do not apply to weights a state legally allowed on July 1, 1956, so a state limit or permit can sit above the federal figure.
In metric terms, the tandem's 51,000 lb gross is 23,133 kg and its 13.25-ton payload is 12.02 tonnes. Outside the US, the national or permit gross limit takes the place of the bridge formula in any dump truck load calculator estimate.
Weighing Out Versus Cubing Out by Material
A truck weighs out when it reaches the legal payload before the bed is full, and cubes out when the bed fills first. Dense soil and stone weigh out in most trucks, which is why a dump truck can be overweight before the bed is full.
| Material | Loose (lb/yd³) | Tandem Tons | Tandem yd³ | Tri-Axle Tons | Tri-Axle yd³ |
|---|---|---|---|---|---|
| Earth, dry packed | 2,550 | 13.25 | 10.39 | 15.50 | 12.16 |
| Earth, wet excavated | 2,700 | 13.25 | 9.81 | 15.50 | 11.48 |
| Loam | 2,100 | 12.60 (cubes out) | 12.00 | 15.50 | 14.76 |
| Clay, natural bed | 2,800 | 13.25 | 9.46 | 15.50 | 11.07 |
| Clay, dry | 2,500 | 13.25 | 10.60 | 15.50 | 12.40 |
| Sand, dry | 2,400 | 13.25 | 11.04 | 15.50 | 12.92 |
| Sand, wet | 3,100 | 13.25 | 8.55 | 15.50 | 10.00 |
| Sand and gravel, dry | 2,900 | 13.25 | 9.14 | 15.50 | 10.69 |
| Gravel, 1/4 to 2 in | 2,850 | 13.25 | 9.30 | 15.50 | 10.88 |
| Gravel, pit run | 3,250 | 13.25 | 8.15 | 15.50 | 9.54 |
| Crushed stone | 2,700 | 13.25 | 9.81 | 15.50 | 11.48 |
| Topsoil | 1,600 | 9.60 (cubes out) | 12.00 | 12.80 (cubes out) | 16.00 |
Only topsoil and loam fill a 12 yd³ tandem without passing 13.25 tons. Topsoil cubes out on the tri-axle too, at 12.8 tons, so sideboards on a topsoil truck add tons per trip, while on gravel they only add overweight risk.
A loader operator filling by eye works to a full bed. For pit run gravel that is 19.5 tons in a tandem, 6.25 tons past its payload, so dump truck load calculator tons, not the bed rating, set the fill.
The weigh-out point in a dump truck load calculator check is the payload divided by the bed. A 12 yd³ tandem with 26,500 lb of payload weighs out on any material above 2,208 lb/yd³ loose, and a 16 yd³ tri-axle with 31,000 lb above 1,938 lb/yd³.
Wet Dirt, Dry Dirt and Swell From the Bank
Wet dirt weighs more than dry dirt. In the Caterpillar tables, loose wet excavated earth runs 2,700 lb/yd³ against 2,550 for dry packed earth, and wet sand runs 3,100 lb/yd³ against 2,400 for dry sand, a 29% rise.
Water changes the yards per load in a dump truck load calculator count, not the tons. A tandem carries 11.04 loose yd³ of dry sand at its payload but only 8.55 yd³ of wet sand, and 100 bank yd³ grows from 135 to 175 tons, or from 11 loads to 14.
Swell is the gain in volume from bank to loose. A common rule of thumb puts rock and stone at 30 to 40%, yet the Caterpillar crushed stone pair of 4,500 lb/yd³ bank and 2,700 loose works out to 66.7%.
S is the swell in percent, with Db and Dl the bank and loose densities of one material. For dump truck load calculator inputs, taking both from one row avoids pairing a swell figure from one source with a weight from another.
| Material | Bank (lb/yd³) | Loose (lb/yd³) | Loose (kg/m³) | Swell |
|---|---|---|---|---|
| Earth, dry packed | 3,200 | 2,550 | 1,513 | 25.5% |
| Earth, wet excavated | 3,400 | 2,700 | 1,602 | 25.9% |
| Loam | 2,600 | 2,100 | 1,246 | 23.8% |
| Clay, natural bed | 3,400 | 2,800 | 1,661 | 21.4% |
| Clay, dry | 3,100 | 2,500 | 1,483 | 24.0% |
| Sand, dry | 2,700 | 2,400 | 1,424 | 12.5% |
| Sand, wet | 3,500 | 3,100 | 1,839 | 12.9% |
| Sand and gravel, dry | 3,250 | 2,900 | 1,721 | 12.1% |
| Gravel, 1/4 to 2 in | 3,200 | 2,850 | 1,691 | 12.3% |
| Gravel, pit run | 3,650 | 3,250 | 1,928 | 12.3% |
| Crushed stone | 4,500 | 2,700 | 1,602 | 66.7% |
| Topsoil | 2,300 | 1,600 | 949 | 43.8% |
Topsoil swells 43.8%, so a 100 bank yd³ strip becomes 143.75 loose yd³ and fills 12 tandem loads at 9.6 tons each. Fill brought in to raise a grade is a separate estimate, covered by the Fill Dirt Calculator.
Bed Sizes From 10 to 16 Yards in Tons
A 10 yard dump truck holds 12.8 tons of dry packed earth, 14.2 tons of 1/4 to 2 in gravel or 8.0 tons of topsoil when filled level. A 15 yard truck holds 19.1, 21.4 and 12.0 tons of the same materials.
| Material | 10 yd³ | 12 yd³ | 14 yd³ | 15 yd³ | 16 yd³ |
|---|---|---|---|---|---|
| Earth, dry packed | 12.8 | 15.3 | 17.9 | 19.1 | 20.4 |
| Earth, wet excavated | 13.5 | 16.2 | 18.9 | 20.2 | 21.6 |
| Clay, natural bed | 14.0 | 16.8 | 19.6 | 21.0 | 22.4 |
| Sand, dry | 12.0 | 14.4 | 16.8 | 18.0 | 19.2 |
| Sand, wet | 15.5 | 18.6 | 21.7 | 23.2 | 24.8 |
| Gravel, 1/4 to 2 in | 14.2 | 17.1 | 19.9 | 21.4 | 22.8 |
| Gravel, pit run | 16.2 | 19.5 | 22.8 | 24.4 | 26.0 |
| Crushed stone | 13.5 | 16.2 | 18.9 | 20.2 | 21.6 |
| Topsoil | 8.0 | 9.6 | 11.2 | 12.0 | 12.8 |
These are full-bed weights in US tons, the volume side of a dump truck load calculator check, not legal loads.
A 3-axle truck at a 20 ft bridge and 24,500 lb tare may carry 13.25 tons, and no more than 14.75 tons at any bridge. A 15 yd³ body of gravel or wet sand needs more axles or a state limit to run full.
Dump truck yards per load for dense material fall well below the bed size. A 16 yd³ tri-axle carries 9.54 yd³ of pit run gravel at its 15.5-ton payload, so an order placed by the yard assumes a fill the weight limit won't allow.
Base rock and asphalt follow the same weight rule. For hot mix, the Asphalt Calculator Tons gives the tonnage that a dump truck load calculator count then splits into trips.
Payload Ratings Like 20 Ton and 25 Ton
A 20 ton dump truck carries 40,000 lb of payload, which is 15.7 loose yd³ of dry packed earth or 14.0 yd³ of 1/4 to 2 in gravel. A 25 ton truck carries 19.6 yd³ of that earth or 17.5 yd³ of the gravel.
| Material | yd³ in 20 Tons | yd³ in 25 Tons |
|---|---|---|
| Earth, dry packed | 15.7 | 19.6 |
| Loam | 19.0 | 23.8 |
| Clay, natural bed | 14.3 | 17.9 |
| Sand, dry | 16.7 | 20.8 |
| Sand, wet | 12.9 | 16.1 |
| Gravel, pit run | 12.3 | 15.4 |
| Crushed stone | 14.8 | 18.5 |
| Topsoil | 25.0 | 31.2 |
Under federal limits a 3-axle truck can't carry 20 tons at all, since its axles stop it at 54,000 lb. Four axles at a 27,000 lb tare need a 38 ft bridge for 67,000 lb, and 5 axles at 30,000 lb need 35 ft for 70,000 lb.
| Axles | Empty (lb) | 20 Tons: Gross / Bridge | 25 Tons: Gross / Bridge |
|---|---|---|---|
| 3 | 24,500 | Over the 54,000 lb axle cap | Over the 54,000 lb axle cap |
| 4 | 27,000 | 67,000 lb / 38 ft | Over the 74,000 lb axle cap |
| 5 | 30,000 | 70,000 lb / 35 ft | 80,000 lb / 51 ft |
| 6 | 32,000 | 72,000 lb / 30 ft | 82,000 lb, over the cap |
For a dump truck load calculator run on the Interstate, 25 tons sits at the payload ceiling. A 5-axle belly dump at a 30,000 lb tare and 51 ft reaches exactly 25 tons, while a 32,000 lb end dump on the same spread stops at 24.
Hauling Rates per Hour, Load or Ton
An hourly rate turns into a load price through the full cycle, loading plus round trip, and into a ton price through the tons per load. At $125 an hour, 5 minutes to load and a 45-minute round trip, a tandem load costs $104.17, or $7.86 per ton.
Ct is the cost per ton, R is the hourly truck rate, t is the full cycle in minutes, loading time plus the round trip with dumping, and P is the tons per load from the weight check, not the bed rating.
| Full Cycle (min) | Per Load at $125/h | Per Ton, Tandem 13.25 t | Per Ton, Tri-Axle 15.5 t | Per Loose yd³, Tandem Earth |
|---|---|---|---|---|
| 30 | $62.50 | $4.72 | $4.03 | $6.01 |
| 50 | $104.17 | $7.86 | $6.72 | $10.02 |
| 60 | $125.00 | $9.43 | $8.06 | $12.03 |
| 100 | $208.33 | $15.72 | $13.44 | $20.05 |
Pricing by the ton pays for what moves, while pricing by the load pays for the trip. On light material the gap shows: a tandem of topsoil cubes out at 9.6 tons, so the same $104.17 load works out to $10.85 per ton against $7.86 for earth.
Dump truck rates per ton therefore follow the cycle time more than the truck. Doubling the full cycle from 50 to 100 minutes doubles the per-ton price, which is how to calculate dump truck rates for a longer haul before asking for quotes.
In dump truck load calculator cost math, hourly billing counts truck hours, not job hours. The 13 tandem loads at a 50-minute cycle come to 10.83 truck hours, or $1,354.17 at $125, whether one truck runs 10.83 hours or 4 trucks finish in 3.33.
| Trucks | Trips Each | Job Hours | Cost at $125/h |
|---|---|---|---|
| 1 | 13 | 10.83 | $1,354.17 |
| 2 | 7 | 5.83 | $1,354.17 |
| 3 | 5 | 4.17 | $1,354.17 |
| 4 | 4 | 3.33 | $1,354.17 |
| 7 | 2 | 1.83 | $1,354.17 |
| 10 | 2 | 1.83 | $1,354.17 |
| 13 | 1 | 1.83 | $1,354.17 |
The trucks that keep a loader busy equal the full cycle divided by the loading time, rounded up. At a 50-minute cycle and 5 minutes a truck that is 10 trucks, since the first one returns as the tenth pulls away full.
N is the truck count, tl is the loading time per truck and tr is the round trip, both in minutes. Trucks beyond N only wait in line at the loader without moving dirt any faster.
Job hours in a dump truck load calculator estimate are the longer of the truck rounds and the loader's own pace. A 13-load job can't finish faster than 13 × 5 + 45 = 110 minutes, or 1.83 hours, so 7 trucks already reach that floor.
Loading time per truck follows the machine's digging rate, which the Excavator Productivity Calculator works out.
Trailer Loads for a 7x14 Dump Trailer
A 7x14 dump trailer box of 168 by 81.5 in with 18 in sides holds 5.28 yd³ level. At a 14,000 lb rating and 3,150 lb empty, its 10,850 lb payload stops dry packed earth at 4.25 yd³, about 80% of the box.
L, W and H are the inside length, width and side height in feet, and 27 turns cubic feet into cubic yards. A nominal 7 ft trailer measures 81.5 in, or 6.79 ft, between the walls, so the inside width belongs in the box math.
Those box, weight and payload figures are the ones Carry-On lists for its 14K low profile 7x14. Other builds differ in side height and empty weight, and both change the yards per trip.
| Material | Tons per Load | yd³ per Load | Box Used |
|---|---|---|---|
| Earth, dry packed | 5.43 | 4.25 | 80.5% |
| Sand, dry | 5.43 | 4.52 | 85.6% |
| Gravel, 1/4 to 2 in | 5.43 | 3.81 | 72.1% |
| Crushed stone | 5.43 | 4.02 | 76.1% |
| Gravel, pit run | 5.43 | 3.34 | 63.2% |
| Loam | 5.43 | 5.17 | 97.8% |
| Topsoil | 4.23 (cubes out) | 5.28 | 100% |
Taller 24 in sides would raise the box to 7.04 yd³, but only topsoil gains, from 5.28 to 6.78 yd³ per trip. Every other material in the table already weighs out with the 18 in sides.
For a 7x14 dump trailer, a dump truck load calculator count is mostly about weight. On the 160-ton earth job, the trailer takes 30 trips against 13 for a tandem and 7 for a belly dump.
The tow vehicle's own towing and combined weight ratings can sit below the trailer's 14,000 lb, and the lower figure sets the dump truck load calculator payload.
Driveway stone often arrives this way, and the Gravel Driveway Calculator gives the tons to split into trips.
Truckload Answers on Limits, Tons and Yards
Each answer uses the same dump truck load calculator inputs: Caterpillar loose densities and the federal limits above, in US tons of 2,000 lb. One US ton is 0.907 metric tonnes, so a 13.25-ton tandem load is 12.02 tonnes.
What is a dump truck load calculator?
It is a trip count built on two limits, the weight of a full bed and the legal payload. Total tons divided by the smaller of the two, rounded up, gives the loads, and the remainder shows how light the last trip runs.
How many loads can a dump truck haul without breaking axle weight limits?
For a dump truck load calculator answer, divide the job's tons by the legal payload and round up. For 160 tons of dry earth that is 13 tandem loads at 13.25 tons, 11 tri-axle loads at 15.5 tons or 7 semi loads at 24 tons.
The legal payload already counts the axle caps of 20,000 lb per single axle and 34,000 lb per tandem pair. The load still has to sit evenly, since a pile heaped over the front of the bed can overload the steer axle alone.
How many tons is 1 truckload?
One tandem truckload of dry earth is 15.3 tons with the 12 yd³ bed full, but 13.25 tons at a 51,000 lb federal gross. A full 16 yd³ tri-axle holds 20.4 tons, and its legal load at 24 ft is 15.5 tons.
Can I convert dump truck loads to tons?
Multiply loads by the tons each one actually carried, not by the bed size. Ten tandem loads of 1/4 to 2 in gravel at the 13.25-ton payload are 132.5 tons, while 10 full 12 yd³ beds of it would read 171 tons.
Scale tickets beat any dump truck load calculator figure when they exist. Without them, tons equal loose cubic yards times the loose density in lb/yd³, divided by 2,000, using the density for that material's moisture.
How many cubic yards fit in a dump truck?
A tandem bed is commonly 12 yd³, a tri-axle 16, a belly dump 22 and a semi end dump 29. The yards that legally ride in it depend on weight: a tandem carries 8.15 yd³ of pit run gravel but a full 12 yd³ of topsoil.
How many tons of dirt are in a tri-axle dump truck?
A full 16 yd³ tri-axle holds 20.4 tons of dry packed earth and 21.6 tons of wet excavated earth. At 58,000 lb gross for 4 axles at 24 ft and a 27,000 lb tare, the legal dump truck load of dirt is 15.5 tons, or 12.16 yd³.
Can a dump truck carry 200 tons?
Not on a public road. The 80,000 lb federal cap holds a semi end dump to about 24 tons, so 200 tons takes 9 semi loads, 13 tri-axle loads or 16 tandem loads. Trucks in the 200-ton class are off-highway mining haulers.
Why not load trucks to 100% of rated capacity?
Moisture and loader error push the weight past the limit. A tandem loaded to exactly 13.25 tons of dry sand holds 11.04 yd³, and if rain brings that sand to 3,100 lb/yd³ the same volume weighs 17.1 tons.
A margin under the dump truck load calculator payload absorbs that swing, and weighing the first load sets a fill line for the rest. Running heavy also adds wear to tires, brakes and springs on every trip.
What if I only know the project dimensions?
Multiply length, width and depth in feet and divide by 27 for bank cubic yards, then weigh it with the bank density. A 40 × 20 ft dig 3 ft deep is 88.89 bank yd³, 142.22 tons of dry earth and 11 tandem loads in a dump truck load calculator count.
Sloped cuts change the volume a lot. The Excavation Slope Calculator adds the side slopes to the in-place yards before any dump truck load calculator split into trips.